Project Timelines Under The Current Schedule.
| Allied Feeds Project | |
| Aug 2005 - Jan 2006 | Site establishment |
| Mar 2006 - May 2009 | Excavation of soil for treatment |
| May 2006 - Jun 2009 | DTD treatment of soil |
| Jun 2009 - Jul 2009 | Decommissioning of DTD plant |
| Jun 2009 - Aug 2009 | Final reinstatement & grading of site |
Lednez Project | |
| May 2005 - Jan 2006 | Site establishment |
| Feb 2006 - Feb 2007 | Excavation of Stage 1 land area |
| Jun 2006 - Sep 2007 | Excavation of Stage 2 land area |
| Apr 2006 - May 2010 | Excavation of Stage 3 land area |
| May 2008 - Aug 2010 | Bay sediment excavation/reinstatement |
| Nov 2008 - May 2010 | DTD treatment of soil and sediment |
| May 2010 - Jun 2010 | Decommissioning of DTD plant |
| May 2010 - Feb 2011 | Final reinstatement & grading of site |