Rhodes Remediation

Syndicate

Syndicate content

Project Timelines

Project Timelines Under The Current Schedule.        

 Allied Feeds Project         
 Aug 2005 - Jan 2006 Site establishment
 Mar 2006 - May 2009 Excavation of soil for treatment
 May 2006 - Jun 2009 DTD treatment of soil
 Jun 2009 - Jul 2009 Decommissioning of DTD plant
 Jun 2009 - Aug 2009 Final reinstatement & grading of site

 

 Lednez Project 

 
 May 2005 - Jan 2006 Site establishment
 Feb 2006 - Feb 2007 Excavation of Stage 1 land area
 Jun 2006 - Sep 2007 Excavation of Stage 2 land area
 Apr 2006 - May 2010 Excavation of Stage 3 land area
 May 2008 - Aug 2010 Bay sediment excavation/reinstatement
 Nov 2008 - May 2010 DTD treatment of soil and sediment
 May 2010 - Jun 2010 Decommissioning of DTD plant
 May 2010 - Feb 2011 Final reinstatement & grading of site